In week 1 the Expected Use column is a value consisting of two parts added together:
- **Planned Consumption** = The required consumption of the product in the production of finished product planned for that week extracted from the Sales Production spreadsheet
- **Scheduled Consumption** = Any open works orders in SAPMAN for finished products that will consume the bulk product when it is completed. It only looks at open orders dues to be started before the end of week 1.
At the start of the planning process it can be assumed that no works orders have been created for week 1. So there is no scheduled consumption for week 1 requirements. Any consumption needed for open works orders will be for production that is the result of late consumption for production scheduled previously.
When reviewing the planning process part way through week 1, it can be assumed that the works orders have been created in SAPMAN for week 1 and may be partially or fully completed. That means all Planned Consumption for week 1 has been Scheduled.
In the top line there is a Yes/No field to indicate if Planned consumption has been scheduled for week 1 (ie Works orders created for week 1 finished product production).
In the calculation of Expected Use in week 1, if the field says "Y" then the Planned Consumption is ignored (as it is included in the scheduled consumption value). If the field says "N" then scheduled production is assumed to be late finishing previously scheduled production and Planned consumption is included in the calculation of expected usage.
In Week 2 onwards incomplete scheduled consumption is ignored and only the planned consumption is included in the calculation.