How to Add and Manage Issues on InEight- Delete
Cinthya Hayes
|
32 steps
|
3 minutes
Ineight
1
Navigate to [https://total-western.hds.ineight.com/AppCore/UserLandingView](https://total-western.hds.ineight.com/AppCore/UserLandingView)
2
Click here the 3 lines.
3
Click "All projects & organizations".
4
Open the project you are looking for. In this case is MATRIX Tank 10 Foundation
5
Under Progress, click "Daily planning".
6
Click the plan name to open the daily plan you are looking for. In this case the name of the daily plan is Chevron.
7
Click "NOTES / ISSUES".
8
Click here. the "+" sign.
9
Click "Add issue".
10
Type the issue name and select the date.
11
Click "Done".
12
Click "Add associations".
13
If applicable, under the employee tab, select the name of the employee.
14
If applicable, under the equipment tab, select the name of the equipment.
15
If applicable, under the component tab, select the name of the component.
16
Click "Done".
information ordinal icon
If the iPad is sync, you will be able to see all the issues created on Progress in Change.
information ordinal icon
Issues should be imported through to change when the daily plan is approved.
17
Click the 3 lines .
18
Select ">" next to the project name, to open the project menu.