How to Add and Manage Issues on InEight
2 minutes
Ineight
1
Navigate to [https://total-western.hds.ineight.com/AppCore/UserLandingView](https://total-western.hds.ineight.com/AppCore/UserLandingView)
2
Click here the 3 lines.
3
Click "All projects & organizations".
4
Navigate to the desired project, which, in this instance, is 'HONEYWELLTORR Heater 6.
5
Under Progress, click "Daily planning".
6
Click on the plan's name to access the specific daily plan you're seeking. In this particular case, the daily plan is titled " Daily Plan 1".
7
Click "NOTES / ISSUES".
8
Click here. the "+" sign.
9
Click "Add issue".
10
Type the issue name and select the date.
11
Click "Done".
12
Click "Add associations".
13
If applicable, under the employee tab, select the name of the employee.
14
If applicable, under the equipment tab, select the name of the equipment.
15
If applicable, under the component tab, select the name of the component.
16
Click "Done".
information ordinal icon
If the iPad is sync, you will be able to see all the issues created on Progress in Change.
information ordinal icon
Issues should be imported through to change when the daily plan is approved.
17
Click the 3 lines.
18
Select ">" next to the project name, to open the project menu.