    Click "Processes"
    Click this button field.
    Click "Construction Change Order (CO11)"
    Download "HECO-11 Construction Change Order" and complete spreadsheet.
    Complete all required fields starred in red.
    Add all FCOs that should be bundled into this change order. Click "FCO"
    Click Attach Existing button.
    Ensure that all FCOs that are going to be bundled are in pending status and in the FCO HOLD STEP.
    Click the checkbox next to all FCOs that are going to be bundled into the change order.
    Click Attach Existing button.
    Click this button.