    NPI - Generate a Project "Cost To Complete Log Report"

    • George Williamson |
    • 7 steps |
    • 2 minutes
    1
    Navigate to [https://mingle-portal.inforcloudsuite.com/KZD6NSW29LEAGLBY_TRN/8629aec6-0469-46e1-ad22-8d4fb7db6c2d?favoriteContext=Projects&LogicalId=lid://infor.syteline.csi](https://mingle-portal.inforcloudsuite.com/KZD6NSW29LEAGLBY_TRN/8629aec6-0469-46e1-ad22-8d4fb7db6c2d?favoriteContext=Projects&LogicalId=lid://infor.syteline.csi)
    2
    Click "Cost To Complete Snap Shot" - This must be done first in order for the Log Report to process all the costs.
    3
    Click "Process" - Select the Project Number and leave the balance blank to pick up all the Tasks and Cost Codes for the Project.
    4
    Click "OK" - the system should summarize all the Project Cost Details and summarize the number processed.
    5
    To get the Report for all of the Cost processed in the prior step run the "Cost To Complete Log Report"
    6
    Click "Preview" to confirm the results then print if desired.
    7
    End of the procedure.