Reports that Contrack can Automatically Generate
David Guinane
6 steps
21 seconds
Contrack
Progress Claim by Lots
1
This report shows which Lots were certified against each Schedule Item in the current Claim Period. In the example below, under each Schedule Item, it will show if a Lot and/or Lots were certified against that Item in August 2024.
Progress Claim Report
2
A report that shows what has been certified to date, what the Contractor claimed this period, and what the Administrator certified this period.
Progress Claim Summary
3
A summary report that shows the payment status of each Schedule.
Lot Status Report
4
A report that shows all Lot's open, closed, guaranteed or guaranteed greater than 1 month.
Lot Status by Schedule Item
5
Similar to the Progress Claim by Lot report that it shows which Lots have been paid against Schedule Items, however this report is a history of the entire job as it shows which periods those Lots they were paid in. It combines all previous periods and progress claims in one report.
Schedule of Differences
6
A report that shows the differences between the Contractors claimed amounts and the Administrators certified amount, and provides a difference comment as to why.
Reports that Contrack can Automatically Generate
David Guinane
6 steps
21 seconds
Contrack
Progress Claim by Lots
1
This report shows which Lots were certified against each Schedule Item in the current Claim Period. In the example below, under each Schedule Item, it will show if a Lot and/or Lots were certified against that Item in August 2024.
Progress Claim Report
2
A report that shows what has been certified to date, what the Contractor claimed this period, and what the Administrator certified this period.
Progress Claim Summary
3
A summary report that shows the payment status of each Schedule.
Lot Status Report
4
A report that shows all Lot's open, closed, guaranteed or guaranteed greater than 1 month.
Lot Status by Schedule Item
5
Similar to the Progress Claim by Lot report that it shows which Lots have been paid against Schedule Items, however this report is a history of the entire job as it shows which periods those Lots they were paid in. It combines all previous periods and progress claims in one report.
Schedule of Differences
6
A report that shows the differences between the Contractors claimed amounts and the Administrators certified amount, and provides a difference comment as to why.